Co-author Gunner West
In Byrne Oil Co. v. Walraven, a court of appeals held that a surface owner/lessor cannot bury his lessee’s pipelines and recover costs when adequate time exists to pursue judicial remedies, even after years of operator delay.
The oil and gas lease required the lessee to “bury pipeline[s] below plow depth” when requested. Walraven purchased the surface in 2016 and immediately requested burial of over 10,000 feet of above-ground flow lines. Lessee Byrne Oil (successor-in-interest of the original lessee) refused, claiming improper notice under the lease’s breach-notification provision. Byrne Oil sued for declaratory relief in 2019; Walraven counterclaimed for breach of the lease and sought an injunction.
Eighteen months into litigation, Byrne Oil buried most lines for a cost of $7,385. Apparently not a believer in comparison shopping, Walraven later hired a third party to bury the remaining 1,300 feet, which cost him $60,240. The trial court awarded Walraven $30,000 as partial reimbursement, finding the full amount he paid excessive. Byrne Oil appealed.
Judicial remedy not exclusive
The appellate court rejected Byrne Oil’s first argument that the lease’s notice provision limited Walraven to judicial remedies. The court explained that the 60-day notice requirement protects lessees from forfeiture by allowing time to cure defaults—it does not establish an exclusive remedy structure. The lessee could propose such a provision, but it goes without saying that not many lessors would find that to be in their best interest.
The suit was for nuisance, not trespass
The court then characterized Walraven’s claims as nuisance rather than trespass. Because the unburied pipelines interfered with Walraven’s use and enjoyment of the surface (not his exclusive possession given that the mineral estate is the dominant estate), the violation constituted a nuisance. The court recognized three remedies for private nuisances: damages, injunctive relief, and self-help abatement; however, not all are available in every case.
The court relied on Martin v. Martin, 246 S.W.2d 718 (Tex. App.—Fort Worth 1952), which held self-help abatement unavailable “where there is time and opportunity for the interposition of an adequate legal remedy.” The court emphasized that self-help exists only for injuries requiring immediate remedy that cannot wait for the ordinary forms of justice. If there is sufficient time to seek legal process, the privilege fails.
Here, the lawsuit had been pending for more than two years when Walraven hired the third-party contractor. Walraven had already pleaded for injunctive relief. The court found this timeframe provided adequate opportunity for judicial remedy, distinguishing cases where plaintiffs sought court orders rather than acting unilaterally.
Policy reasons for the limitation
The court reinforced this holding with oil-and-gas-specific policy: the lessee, as owner and operator of production equipment, “is better suited to either perform the work of relocating production equipment or retain a third party to perform such work.” Allowing surface owners to move equipment risks “disturbing mineral production as well as creating an environmental risk in the event of an accident.” While acknowledging Walraven’s frustration after five years of delay, the court held that “frustration [] cannot justify self-help when the legal remedies of damages and injunctive relief were available.”
The court reversed the $30,000 self-help award but affirmed $1,869.32 for Walraven’s costs to establish his enforcement right. The $125,000 attorneys’ fee award in Walraven’s favor was reversed and remanded for reconsideration.
Your musical interlude, as the appellants say to the trial court (straight out of Bakersfield?).







